PerpEquities

İşlem fikirleri

AI Data Centers

Where the listed neoclouds (Applied Digital, CoreWeave, IREN, Nebius Group, TeraWulf) and the hyperscalers (Alphabet, Amazon, Meta Platforms, Oracle, SpaceX) build AI data centers: how much capacity is announced, contracted, under construction and live - and where projects slip or meet resistance. Every figure links its source, a shared campus counts once, and estimates are marked.

Choose what the map and the lists show

or one company:

Neoclouds GPU clouds and AI-infrastructure landlords

Hyperscalers cloud and AI giants that build for themselves

Infrastructure partners hosts and landlords of the companies above

Active sites113every campus counted once, whoever owns or rents it · 1 withdrawn or paused site kept on record, not counted
Planned / contracted7.16 GW server load · 19.13 GW grid powerserver load and grid power are never added together
Operational capacity980 MW server load · 208 MW grid powerserver load = what reaches the computers; grid power = what the sites draw, incl. cooling
Server load vs. grid power - what's the difference?

Grid power (also called gross or utility power) is what a data center draws from the power grid. Server load (also called IT load) is the part that actually reaches the computers - the AI chips, servers and network. The difference goes into cooling, power conversion and the rest of the building.

Example: Helios Data Center Campus, Helios I, Phase I - 200 MW from the grid, 133 MW for the servers [source]
200 MW grid power
  • In this tracker, 7 project phases publish both figures: grid power is 1.3× to 1.5× the server load (typically 1.5×).
  • Companies usually publish only one of the two. Site pages always show the published figure. To compare companies anyway, the Statistics tab converts the missing measure at the typical ratio above and marks those figures with ~ - an estimate, because the ratio differs from site to site.
  • Reading tip: server load says how much AI computing a site can run; grid power says how much the power grid has to deliver.
  • Operational
  • Partly operational
  • Under construction
  • Contracted / power secured
  • Announced
  • Delayed
  • Reported problem
  • Bubble = planned size, as server load (grid-power-only sites converted for the bubble size)

Data centers on the map 114

Every publicly located AI data center of all companies. The map shows exactly these rows; open a row (or a bubble) for its phases, dates and sources.

Each row: name and place · who owns, builds, runs, rents or uses it · planned size and what of it is live, in server load (power for the computers) or grid power (what the site draws, incl. cooling), as the company publishes it · status and next target date.

Reported problems 81 open · 20 resolved

Problems that news and filings report for the data centers of all companies: grid and power, permits, local opposition, water, financing, construction delays. Each row names the problem, the data center and where it is, and the companies behind the site with their roles. Few reports is not the same as few problems.

ProblemData centerCompaniesSeverityStatusAffectedFirst reported
Google withdrew Franklin Township (Indianapolis) rezoning after council and resident oppositionLocal oppositionIndianapolis (Franklin Township), Indiana, United States (approx.)AlphabetDeveloper: AlphabetCriticalConfirmed-22 Sep 2025
Horizon 2-4 delivery to Microsoft slips from Q4 2026 into January (possibly February) 2027Construction delayChildress, Texas, United States (approx.)IRENOwner, operator: IREN · End customer: Microsoft, NVIDIAHighConfirmed-5 Nov 2026
NJDEP fines Vineland site operator DataOne $1.07M for 62 unpermitted gas generatorsEnvironmentVineland, New Jersey, United States (approx.)Nebius GroupOwner, operator: DataOne · Tenant: Nebius Group · End customer: MicrosoftHighConfirmed-27 Aug 2026
Air permit for on-site Bloom fuel-cell microgrid stalled (Supreme Court stay, hearing vacated, no new date)Permits / zoningSanta Teresa, New Mexico, United States (approx.)OracleDeveloper: BorderPlex Digital Assets · Tenant: Oracle · End customer: OpenAIHighConfirmed-25 Aug 2026
Vineland schedule risk: analyst/press reports of delays, Microsoft tightens oversightConstruction delayVineland, New Jersey, United States (approx.)Nebius GroupOwner, operator: DataOne · Tenant: Nebius Group · End customer: MicrosoftHighDisputed140 MW10 Aug 2026
New York Executive Order 62 pauses state permits for data centers of 50 MW or morePermits / zoningLansing, New York, United States (approx.)TeraWulfOwner: Cayuga Operating Company · Developer: TeraWulfHighDisputed320 MW18 Jul 2026
Charles County has not created a zoning path for data centersPermits / zoningMorgantown (Charles County), Maryland, United States (approx.)TeraWulfOwner: GenOn Holdings · Developer: TeraWulfHighReported800 MW2 Jun 2026
Court halted Pine Island construction over environmental review; settlement requires new MPCA-supervised reviewPermits / zoningPine Island, Minnesota, United States (approx.)AlphabetEnd customer: AlphabetHighConfirmed-26 May 2026
Seven additional Entergy gas plants for Hyperion expansion still awaiting LPSC approval (final vote expected December 2026)Grid / powerLouisiana (Richland Parish), United States (approx.)Meta PlatformsOwner: Blue Owl Capital · Owner, developer, tenant: Meta PlatformsHighReported-15 Apr 2026
NAACP Clean Air Act suit over mobile gas turbines powering COLOSSUS IILegalSouthaven, Mississippi, United StatesSpaceXDeveloper: SpaceXHighConfirmed-14 Apr 2026
Lawsuits by Oxmoor Valley neighbors and Greater Birmingham Humane Society challenge zoning approvalLegalBirmingham, Alabama, United StatesNebius GroupOwner, operator: Nebius GroupHighReported300 MW9 Apr 2026
CoreWeave-Poolside Project Horizon arrangement fell apartCustomerFort Stockton (area), Texas, United States (approx.)CoreWeaveDeveloper: Poolside · Tenant: CoreWeaveHighConfirmed250 MW4 Apr 2026
Organised local opposition and petitions against the Lansing / Cayuga Lake data centerLocal oppositionLansing, New York, United States (approx.)TeraWulfOwner: Cayuga Operating Company · Developer: TeraWulfHighConfirmed320 MW15 Oct 2025
Town of Lansing zoning fight: moratorium withdrawn in 2025, application found incomplete, board now drafting a data center banPermits / zoningLansing, New York, United States (approx.)TeraWulfOwner: Cayuga Operating Company · Developer: TeraWulfHighReported320 MW15 Oct 2025
Landowners and advocacy groups sue LPSC over 'Lightning Directive' fast-track used for Meta power plants and transmissionLegalLouisiana (Richland Parish), United States (approx.)Meta PlatformsOwner: Blue Owl Capital · Owner, developer, tenant: Meta PlatformsMediumReported-9 Nov 2026
Satellite analysis flags missing generators/cooling at Horizon 4; unverified report of a generator fireConstruction delayChildress, Texas, United States (approx.)IRENOwner, operator: IREN · End customer: Microsoft, NVIDIAMediumReported50 MW5 Nov 2026
MCEA and residents sue over Hermantown environmental review (AUAR)LegalHermantown, Minnesota, United States (approx.)AlphabetDeveloper: AlphabetMediumReported-5 Nov 2026
Residents' lawsuit against Goochland technology overlay district that makes data centers by-rightLegalVirginia, United States (approx.)AlphabetDeveloper: AlphabetMediumReported-28 Oct 2026
Badajoz: building authorisation still pending; first operations moved from end-2027 to 2028Permits / zoningBadajoz, Extremadura, Spain (approx.)IRENOwner, developer: IRENMediumReported170 MW21 Oct 2026
Muskie 1 GW power expansion awaits Kentucky PSC approval and brings large ratepayer and collateral commitmentsGrid / powerGrayson, Kentucky, United States (approx.)TeraWulfOwner, developer: TeraWulfMediumReported500 MW5 Oct 2026
Minnesota Attorney General challenges Xcel–Google electric service agreement at the PUCGrid / powerPine Island, Minnesota, United States (approx.)AlphabetEnd customer: AlphabetMediumReported-1 Oct 2026
County fact sheet shows Delta Forge 2 completion by end-2028, later than company's 1H 2028 deliveryConstruction delayBrookwood, Alabama, United States (approx.)Applied DigitalDeveloper: Applied Digital · Tenant: Unnamed U.S.-based tier-one / high investment-grade hyperscalerMediumUnclear210 MW24 Sep 2026
Lancaster RAGE appeal of phase-2 approval; court stays zoning hearingLegalLancaster, Pennsylvania, United StatesCoreWeaveOwner: LPE 01 Propco LLC · Developer: Blue Owl Capital, Chirisa Technology Parks, Machine Investment Group · Tenant: CoreWeaveMediumReported-22 Sep 2026
Resident sues to cancel $3.2B in Birmingham tax abatementsFinancingBirmingham, Alabama, United StatesNebius GroupOwner, operator: Nebius GroupMediumReported-11 Sep 2026
ERCOT Batch Zero and Texas governor-ordered audit of large-load interconnectionsGrid / powerSweetwater, Texas, United States (approx.)IRENOwner, developer: IRENMediumReported2 GW27 Aug 2026
Challenge to emergency water authorization for a new wellWaterSanta Teresa, New Mexico, United States (approx.)OracleDeveloper: BorderPlex Digital Assets · Tenant: Oracle · End customer: OpenAIMediumReported-25 Aug 2026
Pecos expansion (~200 MW leasable) in ERCOT Batch Zero 'Studied Load' during governor-ordered auditGrid / powerPecos, Texas, United States (approx.)Core ScientificDeveloper, operator: Core Scientific · Tenant: Advanced Micro DevicesMediumReported200 MW21 Aug 2026
Helios expansion capacity caught in ERCOT Batch Zero audit / community impact reviewGrid / powerAfton, Texas, United States (approx.)Galaxy DigitalOwner, developer, operator: Galaxy Digital · Tenant: CoreWeaveMediumReported-21 Aug 2026
City of Vineland stop-work orders on fuel-cell installation and LNG tank (August 2026)Permits / zoningVineland, New Jersey, United States (approx.)Nebius GroupOwner, operator: DataOne · Tenant: Nebius Group · End customer: MicrosoftMediumReported-13 Aug 2026
Lake Hawkeye start pushed from 2027 to approximately 2029Construction delayLansing, New York, United States (approx.)TeraWulfOwner: Cayuga Operating Company · Developer: TeraWulfMediumConfirmed320 MW5 Aug 2026
CB-4 and CB-5 (336 MW for Fluidstack) pushed back; leases amended to data-hall-by-data-hall commencementConstruction delayBarker, New York, United States (approx.)TeraWulfOwner, developer, operator: TeraWulf · Tenant: Core42, FluidstackMediumConfirmed336 MW5 Aug 2026
Agreed order with MDEQ: all 69 temporary turbines to be removed by July 2027EnvironmentSouthaven, Mississippi, United StatesSpaceXDeveloper: SpaceXMediumConfirmed-31 Jul 2026
Campus to start on Duke Energy bridge power (57 temporary engines) before grid connectionGrid / powerHamlet, North Carolina, United States (approx.)AmazonOwner, developer: AmazonMediumConfirmed-30 Jul 2026
Polaris Forge 3 power: MDU service agreement needs PSC approval; expansion power tied to related-party Base Electron gas plantGrid / powerCenter, North Dakota, United States (approx.)Applied DigitalDeveloper: Applied Digital · Tenant: Unnamed U.S.-based tier-one / high investment-grade hyperscalerMediumReported-22 Jun 2026
Southaven residents' class action over turbine noise and vibrationLocal oppositionSouthaven, Mississippi, United StatesSpaceXDeveloper: SpaceXMediumReported-9 Jun 2026
Advocacy-group and resident opposition and political scrutiny of the Morgantown planLocal oppositionMorgantown (Charles County), Maryland, United States (approx.)TeraWulfOwner: GenOn Holdings · Developer: TeraWulfMediumReported-2 Jun 2026
Union County residents oppose Kenilworth data center; redevelopment agreement pendingLocal oppositionKenilworth, New Jersey, United StatesCoreWeaveOwner, developer, tenant: CoreWeaveMediumReported-18 May 2026
Oliver County data center moratorium, repeal and pending rezoning for Polaris Forge 3Permits / zoningCenter, North Dakota, United States (approx.)Applied DigitalDeveloper: Applied Digital · Tenant: Unnamed U.S.-based tier-one / high investment-grade hyperscalerMediumReported300 MW1 May 2026
Pittsburg County residents oppose Kiowa 'Project Emerald'; tax incentive districts tabledLocal oppositionKiowa, Oklahoma, United States (approx.)IRENOwner, developer: IRENMediumConfirmed1.6 GW21 Apr 2026
Colossus water recycling plant paused; restart committed by Q1 2027WaterMemphis, Tennessee, United StatesSpaceXOwner, operator: SpaceX · End customer: Anthropic, PBCMediumConfirmed-9 Apr 2026
AG Nessel and environmental groups appeal MPSC approval of DTE's 1.4 GW contractsGrid / powerSaline Township, Michigan, United States (approx.)OracleDeveloper: Related Digital · Tenant: Oracle · End customer: OpenAIMediumReported1.4 GW1 Apr 2026
Report that Blue Owl could not place debt for Lancaster; companies say fully fundedFinancingLancaster, Pennsylvania, United StatesCoreWeaveOwner: LPE 01 Propco LLC · Developer: Blue Owl Capital, Chirisa Technology Parks, Machine Investment Group · Tenant: CoreWeaveMediumDisputed-20 Feb 2026
Residents sue Hobart over permit and rezoning for Amazon data centerLocal oppositionHobart, Indiana, United States (approx.)AmazonDeveloper: AmazonMediumReported-8 Feb 2026
Article 78 lawsuit against the Lansing ZBA's 'general processing facility' classificationLegalLansing, New York, United States (approx.)TeraWulfOwner: Cayuga Operating Company · Developer: TeraWulfMediumReported320 MW5 Feb 2026
Morgantown acquisition still not closedOtherMorgantown (Charles County), Maryland, United States (approx.)TeraWulfOwner: GenOn Holdings · Developer: TeraWulfMediumConfirmed800 MW2 Feb 2026
Cayuga Lake water-withdrawal permit and cooling-water plans contestedWaterLansing, New York, United States (approx.)TeraWulfOwner: Cayuga Operating Company · Developer: TeraWulfMediumReported-28 Jan 2026
El Paso Electric's 366 MW McCloud gas plant for Meta contested; ALJs recommend denial unless ratepayers are shieldedGrid / powerEl Paso, Texas, United States (approx.)Meta PlatformsOwner: BlackRock · Owner, developer, tenant: Meta PlatformsMediumReported-26 Jan 2026
Dewatering for next data shells: 35M gallons/day request tabled indefinitely; earlier dry-well complaintsWaterNew Carlisle, Indiana, United States (approx.)AmazonOwner, operator: Amazon · End customer: Anthropic, PBCMediumReported-24 Jun 2025
Securities class action against CoreWeave over third-party developer (Core Scientific) delaysLegalDenton, Texas, United States (approx.)CoreWeaveOwner: City of Denton · Developer, operator: Core Scientific · Tenant: CoreWeave · End customer: OpenAIMediumReported--
Cherokee County noise and resource concerns; county drafting high-impact land-use ordinanceLocal oppositionMarble, North Carolina, United States (approx.)CoreWeaveOwner, operator: Core Scientific · Tenant: CoreWeaveLowReported-6 Nov 2026
Justified final delivery moved from 'early 2028' to Q2 2028Construction delayHawesville, Kentucky, United States (approx.)TeraWulfOwner, developer: TeraWulf · Tenant: Anthropic, PBCLowReported125.6 MW4 Nov 2026
ELN-03 (150 MW 'Building 2') fully delivered October 2026 vs. original 'middle of 2026' targetConstruction delayEllendale, North Dakota, United States (approx.)Applied DigitalOwner, developer, operator: Applied Digital · Tenant: CoreWeaveLowUnclear75 MW2 Oct 2026
Scottish Greens expected to call for moratorium on large-scale data centres; DataVita invites critics to ChapelhallLocal oppositionChapelhall (Airdrie), North Lanarkshire, Scotland, United Kingdom (approx.)CoreWeaveOwner, operator: DataVita · Tenant: CoreWeaveLowReported-30 Sep 2026
Denton City Council process for a data center moratoriumPermits / zoningDenton, Texas, United States (approx.)CoreWeaveOwner: City of Denton · Developer, operator: Core Scientific · Tenant: CoreWeave · End customer: OpenAILowReported-24 Sep 2026
Entergy sought court order to stop disclosure of Google West Memphis contract; expansion demand redactedLegalWest Memphis, Arkansas, United States (approx.)AlphabetOwner, developer: AlphabetLowReported-1 Sep 2026
Political backlash in Independence: councilman recalled, new data-center restrictionsLocal oppositionIndependence, Missouri, United States (approx.)Nebius GroupOwner, developer: Nebius GroupLowReported-1 Sep 2026
Oklahoma large-load tariff and groundwater cooling rules pending for KiowaPermits / zoningKiowa, Oklahoma, United States (approx.)IRENOwner, developer: IRENLowReported1.6 GW27 Aug 2026
Vineland residents sue over constant humming noiseLocal oppositionVineland, New Jersey, United States (approx.)Nebius GroupOwner, operator: DataOne · Tenant: Nebius Group · End customer: MicrosoftLowReported-27 Aug 2026
Early resident objections to the Muskie campus in Kentucky Power territoryLocal oppositionGrayson, Kentucky, United States (approx.)TeraWulfOwner, developer: TeraWulfLowReported-24 Aug 2026
Environmental groups sue state regulators over approvals without an EISEnvironmentPort Washington, Wisconsin, United States (approx.)OracleDeveloper: Vantage Data Centers · Tenant: Oracle · End customer: OpenAILowReported-17 Aug 2026
Brookwood residents' environmental and transparency concerns (Hurricane Creek, NDA, middle school proximity)Local oppositionBrookwood, Alabama, United States (approx.)Applied DigitalDeveloper: Applied Digital · Tenant: Unnamed U.S.-based tier-one / high investment-grade hyperscalerLowReported-7 Aug 2026
Air-quality opposition to ~645 generators; SELC argues one permit should have been requiredEnvironmentHamlet, North Carolina, United States (approx.)AmazonOwner, developer: AmazonLowDisputed-30 Jul 2026
Falls Township town hall: concerns over Delaware River water, generator noise, power pricesLocal oppositionFalls Township, Pennsylvania, United States (approx.)AmazonDeveloper: AmazonLowReported-15 Jul 2026
State AG investigating allegedly fraudulent support letters in the air permit recordLocal oppositionSanta Teresa, New Mexico, United States (approx.)OracleDeveloper: BorderPlex Digital Assets · Tenant: Oracle · End customer: OpenAILowReported-9 Jul 2026
NJ pauses Next New Jersey Program-AI under review (CoreWeave award)FinancingKenilworth, New Jersey, United StatesCoreWeaveOwner, developer, tenant: CoreWeaveLowReported-23 Jun 2026
BC caps new power for data centres; northern BC municipalities push for higher taxes on IREN sitesGrid / powerMackenzie, British Columbia, Canada (approx.)IRENOwner, operator: IRENLowReported-2 Jun 2026
Pine Island water use: up to 55.5 million gallons a yearWaterPine Island, Minnesota, United States (approx.)AlphabetEnd customer: AlphabetLowReported-26 May 2026
Denton residents raise utility-bill and water concerns about data centersLocal oppositionDenton, Texas, United States (approx.)Core ScientificOwner: City of Denton · Developer, operator: Core Scientific · Tenant: CoreWeave · End customer: OpenAILowReported-7 May 2026
Noise and resident concerns over Polaris Forge 3 near Center/HanoverLocal oppositionCenter, North Dakota, United States (approx.)Applied DigitalDeveloper: Applied Digital · Tenant: Unnamed U.S.-based tier-one / high investment-grade hyperscalerLowReported-5 May 2026
830 MW of approved Helios II capacity still without a tenantCustomerAfton, Texas, United States (approx.)Galaxy DigitalOwner, developer, operator: Galaxy Digital · Tenant: CoreWeaveLowConfirmed830 MW28 Apr 2026
NMELC lawsuit against Dona Ana County over project approval/financing proceedsLegalSanta Teresa, New Mexico, United States (approx.)OracleDeveloper: BorderPlex Digital Assets · Tenant: Oracle · End customer: OpenAILowReported-24 Mar 2026
Planned 600 MW Abilene expansion moved away from Oracle/OpenAI; Microsoft leased buildings 9-10CustomerAbilene, Texas, United States (approx.)OracleOwner: Lancium · Developer: Crusoe Energy Systems · Operator: Oracle · End customer: OpenAILowConfirmed600 MW9 Mar 2026
Noise from generators/substation raised at planning commissionLocal oppositionLancaster, Pennsylvania, United StatesCoreWeaveOwner: LPE 01 Propco LLC · Developer: Blue Owl Capital, Chirisa Technology Parks, Machine Investment Group · Tenant: CoreWeaveLowReported-5 Feb 2026
Push on El Paso City Council to cancel Meta data center agreementsLocal oppositionEl Paso, Texas, United States (approx.)Meta PlatformsOwner: BlackRock · Owner, developer, tenant: Meta PlatformsLowUnclear-26 Jan 2026
Boyce/Rapides Parish protests over NDAs, utility bills and environment (Delta Forge 1)Local oppositionBoyce, Louisiana, United States (approx.)Applied DigitalOwner, developer: Applied Digital · Tenant: Unnamed U.S.-based tier-one / high investment-grade hyperscalerLowReported-23 Jan 2026
Off-balance-sheet JV financing with residual value guarantees (Hyperion/Beignet; El Paso venture)FinancingLouisiana (Richland Parish), United States (approx.)Meta PlatformsOwner: Blue Owl Capital · Owner, developer, tenant: Meta PlatformsLowReported-21 Oct 2025
IDEM ordered stop to work in state-regulated waters after contractor filled wetland without authorizationEnvironmentNew Carlisle, Indiana, United States (approx.)AmazonOwner, operator: Amazon · End customer: Anthropic, PBCLowConfirmed-14 Aug 2025
Reports that the Denton site's power demand strains the city's grid capacityGrid / powerDenton, Texas, United States (approx.)CoreWeaveOwner: City of Denton · Developer, operator: Core Scientific · Tenant: CoreWeave · End customer: OpenAILowUnclear-15 Jul 2025
Ellendale community concerns: noise, construction traffic, water trucking, annexation/eminent-domain protestLocal oppositionEllendale, North Dakota, United States (approx.)Applied DigitalOwner, developer, operator: Applied Digital · Tenant: CoreWeaveLowReported-14 May 2025
Second 150 MW grid increment for Colossus 1 depended on TVA approvalGrid / powerMemphis, Tennessee, United StatesSpaceXOwner, operator: SpaceX · End customer: Anthropic, PBCLowReported150 MW2 May 2025